On a steel-framed building, the floor often comes down to two options: composite metal deck with a concrete topping, or precast hollowcore planks. Both work, both get specified, and suppliers on each side will tell you theirs is better.
The useful thing is that this comparison has been studied by the industry bodies, with independent cost consultants doing the pricing. So rather than give you our opinion, here is what that data actually found.
Composite Metal Deck vs Hollowcore: What the Studies Compared
Two published studies put both floors on the same steel frame and cost them side by side.
- Business park office: commissioned by the BCSA and Tata Steel. Gardiner & Theobald priced a three-storey office of around 3,200m², and Mace worked out the programme.
- Secondary school: part of the Costing Steelwork series from the BCSA and Steel for Life. AECOM costed a real three-storey secondary school in Knowsley, Merseyside, at 2023 prices.
Both were funded by the steel sector, and that is worth saying. But both floors being compared sit on a steel frame, so the question was never steel against concrete. It was which floor to put on the steelwork.
Composite Metal Deck vs Precast Cost Comparison
On both buildings, composite deck came out around 10% cheaper than precast planks on the frame and upper floors.
| Building | Composite Deck (£/m²) | Steel + Hollowcore (£/m²) | Frame & Floor Saving | Total Building Saving |
|---|---|---|---|---|
| Secondary school (Knowsley) | £340 | £379 | ~10% | ~2% |
| Business park office | £177 | £196 | ~10% | ~6% |
Frame and upper floors cost per m² of gross internal floor area. See sources below.
The saving is not all in the floor. A composite floor is lighter, so the frame and foundations can be lighter too. In the office study, the composite option had the lowest substructure cost of any frame. A shorter programme brings preliminaries down as well. That is why both studies insist on comparing total building cost, not just the frame and floor package.
Programme: Which Floor Builds Faster?
On the office, Mace found composite deck gave the fastest frame and the fastest overall build, by one week.
We would rather be straight about that margin than dress it up. Deck goes down faster, because several sheets come up in one crane lift, where precast goes in one plank per lift. Some of that gain is given back at stud welding, which takes longer than grouting plank joints. Net, deck was still a week ahead.
Why Composite Metal Deck Saves Time and Money
| Factor | Composite Metal Deck | Precast Hollowcore |
|---|---|---|
| Weight of floor unit | Around 10–15 kg/m² | Around 237 kg/m² (150mm, grouted) |
| Coverage per artic load | Around 600–700m² (MetFloor® 80) | Around 80–110m² |
| Crane lifts | Bundles of sheets per lift. Topping is pumped. | One plank per lift |
- Less weight to lift. The concrete topping on deck is pumped rather than craned, so the crane only handles light bundles of sheet. That lighter dead load is also what lets the frame and foundations come down in size, which is where the studies found much of the saving.
- Fewer vehicle movements. The topping concrete still arrives by mixer, and a composite slab generally needs more of it than a precast screed, so the saving is in the floor units themselves.
- A faster route to a working platform. Once edge protection is up, the first sheet is pushed out and becomes the platform for laying the rest of the bay. The fixed deck then carries the stud welders and the concrete gang without waiting on the crane.
The point worth carrying away
These are two buildings, not every project, and the margins are modest. Precast still has its place, and site access, spans, acoustics and crane strategy can all tip a job either way.
But on typical low-rise steel frames, the published data says composite metal deck is the cheaper overall option. It is worth pricing both properly rather than assuming precast by default.
Composite Floor Decking Design, Supply and Fix
We design, supply and fix composite floor decking across the UK, with through-deck stud welding as part of the package. Send us your structural GA drawings and we will price a deck layout for your frame, so you can compare it with precast on your own project rather than someone else’s.
Want a like-for-like price against precast? Send your GA drawings and we will come back with a deck layout and quote.
Call 01787 275055 or email sales@rmdp.co.uk
Sources
- Secondary school cost model (AECOM, BCSA, Steel for Life) – SteelConstruction.info cost comparison studies
- Business park office study (BCSA, Tata Steel, Gardiner & Theobald, Mace) – Building magazine: multi-storey offices