After a 7 year design project, Burberry finally got feet on site to make a pillar free shop in New Bond Street! This allowed for an open, uninterrupted floor space for shoppers to move around at their leisure free of obstacles.
RMD were enlisted to help design the floor, to coordinate the delivery over 4 phases, and to lift equipment to land metal deck. As the install was in an enclosed area careful consideration to ventilation had to be accounted for. Again the RMD team performed very well under difficult conditions with Forcia teams to deliver a successful project for Burberry!